Sunday, September 27, 2009

Footers : Week 4



We began officially September 1st. As of today, we are at end of Week # 4.
Inspection of foundation and Footers were done this week. Passed the inspection with flying colors. The Well drilling guy didn't show up this past Thursday as scheduled. Hopefully it will happen the coming week.
Central Hudson & Verizon was on site the past week to bring in the phone and electrical service...finally after 6 months of delay.
We also found a cheaper porcelain alternative to marble bathroom tiles. The price is at $12.95/ sq feet, just a small fraction of what marble costs. The Kitchen Bath company is located next to Ikea Paramus, and as expected, it's much more cost effective than looking in Manhattan.
Our LVL/LVM/LVC kit has been rescheduled to deliver on October 12th instead. We decided to push it back 2 weeks due to the rainy whether this summer. The cost of just changing the delivery schedule is $250 admin fee + $200 of storage charges for the month. So just be careful on the scheduling.
Our Fire Orb is schedule for delivery mid coming week (Week #5). The owner of the FireOrb company is really nice and helpful. Love hands on people and especially small business owners who have pride in their product.