Sunday, January 17, 2010
Week: 20 Roof Baby!
The roof materials was finally delivered on 1/14/2010. Work promptly began and progress was smooth thanks to some badly needed pleasant weather. It was in the 40's, pretty good for January weather. Weather proofing materials EPDM membrane was all laid on Saturday. Very lucky since Sunday had some rain in the forecast.
Some bad news: Matt broke his ankle and needs some pins and a cast. Sounds very serious and we all hope for a smooth recovery. Adam has been putting in extra hours and got some of their child hood friends to help while Matt is out.
Other bad news: Due to the issue with the rundown on the slope, we decided to delay the swimming pool and jacuzzi to years down the line. We may just put in a above ground hot tub instead for now and disguise it somehow since we hate the look of the regular hot tubs. Found a good idea in Dwell, we'll see how it works out. The DEC is now fully involved and it seems to be an issue with our entire sub division, not just our lot.
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment