Monday, November 16, 2009

Week 11: Concrete Floors


Biggest item this week was the concrete floors. 5 inches thick and fully dried. We are ready for walls to go up.
Received news this week that the well pump and lines would cost double than we originally thought...bummer! The Distance is more than 450 feet to run the electrical lines from well to the house, and we need a constant pressure pump since we have a low flow rate.